In regards to the optical project that the City of Moscow is working on with
Gritman, MSD, the UI, and the State Transportation Department and Dale says:
"Some things of interest here:
* The cost of the project was estimated at $125,000 with the Citys
portion representing approximately $65,000 of the total.
* The final cost came in at nearly $180k. That's 42.4% higher than
estimated. Not a trivial mistake. "
However, if you read what the City is saying, you see that once again, Dale
got it wrong:
"Upon examination of the bid responses North Skys bid has been determined
to be non-responsive as they failed to acknowledge the two bid document
addendums published during the bid period. Therefore we have only one
responsive bid in the amount of $178,405.00. Staff has identified means of
reducing the project cost by utilizing alternate installation methods for
particular segments of the project, primarily by using aerial instead of
underground installation methods to reach Lena Whitmore Elementary School
and to substitute a microwave connection from Eggan Youth Center to the
Aquatics Center.Staff has worked with Sefnco to establish estimated cost
savings by these modifications and it is estimated that the total project
cost could be reduced to approximately $100,000, with the Citys portion at
approximately $39,000. This would bring the project approximately $25,000
under budget."
If the Council meeting last night was watched you would have heard Bill
state:
"This element has been named the East Side Fiber Optics Project. The cost of
the project WAS(!) estimated at $125,000 with the Citys portion
representing approximately $65,000 of the total. Two bids on the project
were received, one from North Sky Communications and one from Sefnco
Communications in the amounts of $157,182.42 and $178,405.00 respectively."
In other words, what the project IS slated to cost is not what was
originally budgeted - it is LESS! And it is NOT just a project between the
City and MSD, it involves Gritman, UI and the Transportation Department. No
one entity is footing the bill totally.
The monies used by MSD for this project have been set aside for the past
two/three years. It's been an accumulation of Facility monies that have
been set aside and added to over the years. It was started in 2002/03 and
has been sitting there with occasional additions over the years. This is a
project that the MSD knew was going to happen and they have been responsible
enough to add to the fund until the amount needed is reached. It has
nothing to do with the monies that is needed for the fixing of the schools
in Moscow.
J ;)
_________________________________________________________________
Express yourself instantly with MSN Messenger! Download today - it's FREE!
http://messenger.msn.click-url.com/go/onm00200471ave/direct/01/
More information about the Vision2020
mailing list