Question:


·         The GC on a residential construction project (owned by a Trust entity) is being terminated midway through construction.

·         Work has stopped and will remain that way until a new GC is retained.

·         Owner is in the process of hiring a new GC, but we are a few weeks off from the replacement GC being selected.

·         Old GC wants its name off the permit now (before new GC is selected and can be named as the new qualifier on the job).

·         What to do?  Can the Trust be listed on the Change of Contractor form in the interim?

Let me know if anyone has experience with this procedure.  Thanks in advance.

Leslie Tomczak
Board Certified by The Florida Bar in Construction Law
LEED AP
Akerman LLP I 350 East Las Olas Boulevard I Suite 1600 I Fort Lauderdale, FL 33301
Dir: 954.759.8926 I Main: 954.463.2700 I I Fax: 954.463.2224
leslie.tomczak at akerman.com


vCard<http://www.akerman.com/bios/vcard.asp?id=673> | Bio<http://www.akerman.com/bios/bio.asp?id=673>

<http://www.akerman.com/>

[http://www.akerman.com/akermansig.jpg]

CONFIDENTIALITY NOTE: The information contained in this transmission may be privileged and confidential, and is intended only for the use of the individual or entity named above. If the reader of this message is not the intended recipient, you are hereby notified that any dissemination, distribution or copying of this communication is strictly prohibited. If you have received this transmission in error, please immediately reply to the sender that you have received this communication in error and then delete it. Thank you.



-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://mailman.fsr.com/pipermail/clc-discussion/attachments/20150521/0f18955e/attachment.html>


More information about the CLC-Discussion mailing list