More large loads for U.S. 12 discussed by state, Korean firm
Betsy Z. Russell

BOISE – The Idaho Transportation Department met in September with a Korean
firm that wants to move another 40 to 60 giant truckloads of oil equipment
across scenic U.S. Highway 12, and local residents who are suing over four
other proposed shipments didn’t find out until their attorney filed a
public records request.

ITD officials met with half a dozen representatives of Harvest Energy and
its associates on Sept. 15 to discuss the additional oversize truckloads,
proposed to start in June 2011 and travel through Idaho and Montana on the
way to the Alberta oil sands project in Canada. The equipment would travel
from the Port of Vancouver, Wash., to the Port of Lewiston by barge.

Borg Hendrickson and Linwood Laughy, a couple who live along Highway 12,
in an e-mail decried a lack of public input and “closed-door meetings.”

“A single state agency is in the process of changing forever the character
of Idaho’s Clearwater-Lochsa corridor,” they wrote. “This
re-characterization will have profound consequences for the whole of
north-central Idaho.”

ITD spokesman Jeff Stratten said, “They (Harvest Energy) approached us,
and so obviously we’ll sit down and tell them what the requirements
(are).”

He noted that the department is awaiting the Idaho Supreme Court’s ruling
on four mega-loads proposed by ConocoPhillips, which wants to move
equipment wider than the two-lane road from the port in Lewiston to its
Billings refinery.

Imperial Oil/ExxonMobil plans to send 207 oversize shipments along Highway
12 to its Kearl Oil Sands project in Canada, starting in November.

Residents and businesses along the highway, which is officially designated
as the Northwest Passage Scenic Byway and runs along the wild and scenic
Clearwater and Lochsa rivers, sued over the ConocoPhillips proposal, and a
district judge revoked the permits for the four loads. The company and ITD
both appealed to the Idaho Supreme Court; a ruling is pending.

No permits have yet been issued for the larger ExxonMobil project, which
could temporarily block the two-lane route at night five nights a week for
a year as the loads pass through.

“Idahoans will pay the price in personal safety, a diminished tourism
industry, accelerated replacement of damaged highway and bridges, and in
being pushed out of our own land by foreign corporations,” Hendrickson and
Laughy charged.

Adam Rush, another ITD spokesman, said Friday: “The transportation
department and Harvest Energy discussed load dimensions, bridges on U.S.
12, clearances, traffic control plans and the weight of shipments. No
proposals were submitted to ITD by Harvest Energy. June of 2011 was
mentioned as a preliminary start date to move equipment.”

He added, “The department meets routinely with haulers who have questions
about permits.”

---------------------------------------------------------

Question:  Where is Idaho's governor?

Oh . . . that's right.  He's on the campaign trail with his "Capital for a
Day" come-on.

Seeya at the polls, Moscow.

Tom Hansen
Moscow, Idaho

"The Pessimist complains about the wind, the Optimist expects it to change
and the Realist adjusts his sails."

- Unknown




More information about the Vision2020 mailing list