Pumping poop definitely sounds like an improvement, especially given the alternative. Lien it.
Sent via the Samsung Galaxy Note8, an AT&T 4G LTE smartphone
-------- Original message --------From: Alex Barthet <Alex at barthet.com> Date: 3/23/18 3:39 PM (GMT-05:00) To: clc-discussion at lists.flabarrpptl.org Subject: [CLC-Discussion] Lien/Bond Rights of Pump Out Contractor
Afternoon all. Quick question. Any reason to think that a sanitation/lift station pump out company that vacuums out and physically removes waste (human, gray water, …) from a nonfunctioning lift station on a project under construction
DOES NOT have lien or bond rights? Until the lift station was functional, they could not get a CO. I see it just like a construction dumpster/waste hauling company. Thoughts?
Thanks and have a great weekend.
Regards,
Alex Barthet
Board Certified in Construction Law
TheLienZone Construction Law Blog
vCard |
Biography
The Barthet Firm
200 S. Biscayne Blvd., Suite 1800
Miami, Florida 33131
305-347-5295 (direct line)
alex at barthet.com
www.barthet.com
This electronic communication may contain privileged, confidential, or proprietary information. If you are not the intended recipient or an authorized agent of the intended recipient, please delete this communication and notify the sender.
Thank you.
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://mailman.fsr.com/pipermail/clc-discussion/attachments/20180323/b44a3285/attachment.html>
More information about the CLC-Discussion
mailing list